I haven’t written much about the I-5 interchange plan and you probably haven’t heard about it because the process is slow and complicated. But big things are in the work for the one mile area where the I-5 runs through the Rose Quarter and Albina neighborhood.

That stretch of I-5 has the highest crash rate of any part of the I-5 in Oregon: 472 crashes over the past five years. The freeway and its on-and-off ramps also slice the Rose Quarter off from the rest of the city, making it a not-so-great place to live or open a business. In a plan (pdf) put together by the city and Oregon Department of Transportation (ODOT), the state will spend years and $400 million to revamp the freeway and surface streets around the Rose Quarter.

A stakeholder group signed off on moving the I-5 interchange plan forward at a key meeting last Thursday, june 7th, but eight out of 18 representatives expressed some or serious concern about the project. Some area residents are frustrated that the long-needed improvements to the surface streets—like the better bike way, pedestrian bridge, and altered traffic flows—can apparently only come coupled with the freeway widening.

Changes to the area would include:

• Widening roughly one mile of I-5 with an auxiliary on-off lane in both directions and shoulders. (cost: $140-150 million)
• “Capping” the freeway where it runs under the Rose Quarter and Broadway/Weidler, building a street-level lid that could be used for a park or buildings.
• Tearing down and rebuilding four freeway overpasses on NE Broadway, NE Weidler, Williams, and Vancouver. (cost of rebuilding the bridges with the lid: $170-190 million)
• Tearing down the freeway overpass on NE Flint.
• Moving the southbound I-5 onramp north one block (from Winning Way to Weidler/Williams).
• Building a two-way cycletrack on North Williams through the area.
• Building a bike/ped bridge from the Rose Quarter over I-5 to the Lloyd District. (cost: $15-20 million)

That all is hard to visualize, so here’s a drawing.

I-5 was built in 1966 and traffic on it has doubled in those years to 120,000 cars a day today. ODOT predicts that the project will reduce crashes on the stretch by 30-50 percent. ” Neighborhood leaders say the city and state should find some way to improve the neighborhood streets without widening the freeway.

Eliot Neighborhood Land Use Chair Mike Warwick described that situation as “the devil’s bargain.” He and two others on the stakeholder committee were critical of spending hundreds of millions of dollars and years of heavy duty construction to add one lane and shoulders to a freeway built less than 50 years ago, but they really want the improved neighborhood street connections that ODOT and the city promise will follow the freeway’s widening.

Neighborhood leaders also worry that when the time comes to do the neighborhood improvements, the city and ODOT will cut corners, lose funding, or otherwise fail to follow through on the neighborhood improvement parts of the plan, leaving the area with a wider freeway but none of the surface-street fixes. This neighborhood is no stranger to well-intentioned redevelopment plans gutting the area—they worry this could be a repeat of the original the ’60s-era freeway planning, when I-5 was rammed through the majority African-American neighborhood with little concern for the freeway’s impact on residents.

“This is maybe the most important thing to happen to Eliot since I-5 went through,” Eliot neighborhood chair Allan Rudwick said at the stakeholder meeting last night. “Pushing this forward will delay development in the area for maybe 10 years. Why would we do that to add one auxiliary lane and shoulders to one mile of freeway?”

Long-time activist Jim Howell was more direct. “We have a nickname for this project: CRC Light,” he told the committee. “It will require massive demolition and reconstruction. We could use that money to repair miles of crumbling city streets.”

For its part, the city and ODOT assured stakeholders last night that the freeway widening and neighborhood street fixes would go hand-in-hand.

“This is considered an extremely significant step forward step from the city and the state,” said city planner Paul Smith. “This is one project and it will need to be funded as a single package.”

Sarah Shay Mirk reported on transportation, sex and gender issues, and politics at the Mercury from 2008-2013. They have gone on to make many things, including countless comics and several books.

12 replies on “We’re Planning to Spend $400 Million to Widen a Freeway Through the Rose Quarter”

  1. 472 crashes in 5 years makes this the highest crash rate on I-5? But the CRC has been claiming that the I-5 bridge sees 1 crash a day on average.

  2. @Reymont – “Most crashes on I-5 in Oregon”. The numbers for the I-5 bridge are split between OR and WA, and I’d be willing to bet the majority of those wrecks are people trying to get on 14 in Vancouver.

  3. Thanks for the coverage of this.

    We need to take the air out of the tires of Vancouver commuter activists, bucket seat motor car ideologues and the highway industrial complex.

    There is plenty of capacity North-South with the combination of I5 and I205 as well as I5 and I405. There is more capacity through Portland than the proposed CRC.

    One suspects that this is a bone thrown to CRC proponents attacking Rose Quarter lanes as a “bottleneck”. They would love to see I5 itself widened to 4 lanes from Vancouver to San Diego at a cost of a billion trillion dollars.

    Most of these upgrades are unnecessary, costly and a developer’s and concrete industry’s wet dream. Yes, we need better bike access through the area. It should be on dedicated cycle tracks, separated from motor traffic. But this Frankenstein construction project is not the solution.

  4. Did anyone else besides the Eliot Nbhd. rep. vote against this huge freeway widening project? Did all the pedestrian, environmental, and bicycle advocates vote for it? Didn’t the pedestrian and bicycle folks vote for the CRC way back? Do we see a pattern here?

  5. @7…that’s nice. Good to know the 25% might have that dream come true. I really don’t see the logic in this project (hey that rhymes) but I also doubt the traffic has only doubled in 46 years. Do you know how many people moved here in the last ten years.?

  6. @Penny Pincher: The stakeholders were asked to vote either “1” if they supported the project, “2” if they supported the project but had concerns, and “3” if they had major concerns. The three people who voted 3 were the reps from Eliot and Irvington and a member of AROW, a progressive transportation group. Five people voted 2, but I didn’t get all their names.

  7. I’m sure these projected costs will remain solid over the “years” this project will take to finish. ODOT = Oregon Department of Outdated Thinking

Comments are closed.